Project management
A client's guide to critical paths, float and the questions worth asking each week.
Marco Ilves
5 min read

A construction programme can look like a wall of bars. Ten minutes is enough to read the parts that matter.
Find the critical path
The critical path is the chain of activities with no spare time. If anything on it slips, the completion date slips. Ask to see it highlighted.
Look at the float
Float is the spare time on everything else. Lots of float is comfort; float being used up week after week is an early warning.
The best weekly question is simple: what changed on the critical path since last week?
Ask about the next six weeks
Long-range dates move. The next six weeks should be firm, resourced and explainable in plain language.