Industrial
A 61,000 m² logistics facility handed over five weeks ahead of programme.
Venlo, NL
2023
Design & build

Weeks ahead of programme
m² floor area
Parallel build zones
A 61,000 m² logistics hub needed to open before the peak season, with a programme already squeezed by late design.
We split the building into four independent zones and ran them in parallel, with steel, slab and cladding teams following each other through the site.
Design-and-build delivery with a precast-and-steel structure, high-flatness floors and roof-mounted solar ready for connection.
Design & build, Groundworks, Steel frame, Floors, External works
Planning something similar?
Four quick questions. A real person reads every request and replies with a budget range by the next working day.