Industrial
Critical power and cooling installation for a 36 MW data hall.
Eemshaven, NL
2024
MEP installation

MW critical load
Prefabricated skids
Days of commissioning delay
A 36 MW data hall with a commissioning date fixed by the client's own customers.
Critical power and cooling were prefabricated off site in skids and tested before they arrived, so site work became assembly.
Fully witnessed integrated systems testing, with every result logged and handed over in a searchable record.
Critical power, Cooling, Prefabrication, Integrated testing